![tile work commences](Thumbnails/31.jpg) tile work commences
11 November 2009 |
![back board in server room](Thumbnails/32.jpg) back board in server room
11 November 2009 |
![tile down to staff entrance](Thumbnails/33.jpg) tile down to staff entrance
11 November 2009 |
![tile down in hall between tech support and kitchen](Thumbnails/34.jpg) tile down in hall between tech support and kitchen
11 November 2009 |
![bulkheads with diffusers in place](Thumbnails/35.jpg) bulkheads with diffusers in place
11 November 2009 |
![ledger for exterior finish attached](Thumbnails/36.jpg) ledger for exterior finish attached
11 November 2009 |
![starting to close in the addition](Thumbnails/37.jpg) starting to close in the addition
12 November 2009 |
![starting to close in the addition](Thumbnails/38.jpg) starting to close in the addition
12 November 2009 |
![more clearing at back of lot](Thumbnails/39.jpg) more clearing at back of lot
12 November 2009 |
![preparing a pad to move the containers on to](Thumbnails/40.jpg) preparing a pad to move the containers on to
12 November 2009 |
![getting the stud wall bases laid out and installed](Thumbnails/41.jpg) getting the stud wall bases laid out and installed
12 November 2009 |
![getting the stud wall bases installed](Thumbnails/42.jpg) getting the stud wall bases installed
12 November 2009 |
![canopy over main entrance](Thumbnails/43.jpg) canopy over main entrance
13 November 2009 |
![inside wall studs started in addition](Thumbnails/44.jpg) inside wall studs started in addition
13 November 2009 |
![tile flooring continues in hall way](Thumbnails/45.jpg) tile flooring continues in hall way
13 November 2009 |